Palms & Company Document


WHAT'S NEW ----- About The Portal To Russia ----- Email Dr. Palms




Foreign Assistance: Assessment of Selected USAID Projects in Russia

(Letter Report, 08-03-95, GAO-NSIAD-95-156).

PART III

THIS DOCUMENT IS IN FOUR PARTS. THIS IS PART III

CLICK FOR PART I, PART II, PART III, PART IV


contract to serve as the program's core contractor and provide the

technical support for its environmental activities in Russia, Kazakstan,

and Ukraine. In April 1994, an initial delivery order was signed to

provide support for activities in Novokuznetsk and the Russian Far East.

Detailed delivery orders were signed for these activities in September

1994. CH2M Hill also serves as the contractor or subcontractor on various

components of the program.

Although the environmental policy and technology project is still ongoing,

USAID officials said its progress so far has been disappointing. Progress

has been slow because CH2M Hill did not fill critical staff positions in

Russia in a timely manner, and it relied on staff located in the United

States to manage the projects. The expanded scope of the Far East

component further contributed to the delay. Further, USAID field staff

lacked authority and information to expedite project implementation. The

projects' expected contributions to systemic reform and long-term benefits

are not likely to be significant.

SECTOR PROBLEM

Severe environmental degradation threatens the physical health and

socioeconomic well-being of people throughout Russia and deters economic

and political restructuring efforts. Environmental problems range from

nuclear safety issues; to pervasive mismanagement of natural resources; to

some of the worst air, water, and land pollution problems in the world.

The breadth and magnitude of the economic, health, and ecological costs

are difficult to quantify, although remediation activities alone are

expected to cost billions.

Environmental problems are exacerbated by many factors, including

inattention to environmental consequences, a lack of economic and

political incentives to use resources efficiently, the inability of

nongovernmental agencies to participate in environmental decision- making,

and the inability of governmental institutions to effectively regulate

state-owned monopolies and curb illegal economic activities.

This information was obtained primarily from USAID's February 1993 Project

Memorandum and the U.S. Government's Environmental Strategy for Russia,

prepared by USAID.

PROJECT OBJECTIVES

Our analysis focused on CH2M Hill's performance as the core contractor and

two projects where it serves as the primary contractor--the Multiple

Pollution Source Management project in Novokuznetsk and the Sustainable

Natural Resources Management and Biodiversity Protection project in the

Russian Far East. Both projects are to run from September 1994 to

September 1997.

The objectives of the $7.4-million core contract are to coordinate all

activities under the core contract, monitor and evaluate the activities

and deliverables, and provide support functions as needed.

The objectives of the Multiple Pollution Source Management project are to

reduce pollution-related health risks and promote environmentally

sustainable economic development; improve public health; reduce pollutant

emissions from industries and cities; assist industries in restructuring

in an environmentally sound and sustainable manner; and strengthen

institutions and train individuals to continue improvements initiated

during the project. The $13.4-million delivery order included $6.3

million for the Novokuznetsk project along with two other projects.

The Sustainable Natural Resources Management project was expanded from a

narrowly focused $3-million, 3-year project focused on fire prevention and

control to a $16.7-million, 5-year project focused on sustainable forest

management and biodiversity protection. This expansion responded to the

Gore-Chernomyrdin Commission's recommendations. Specific project

objectives are to promote sustainable forest management in the

Khabarovskiy and Primorskiy Territories and protect endangered species and

critical habitats in the Khrebet Sikhote-Alin' mountain region. To

address these objectives, the contract specifies 25 tasks for CH2M Hill

and multiple subcontractors. USAID approved a $9.4-million delivery order

for CH2M Hill to implement and coordinate these activities.

The Gore-Chernomyrdin Commission was created in 1993 to overcome trade

barriers in the energy sector, but now includes business development,

space, environment, science and technology, health, and defense

diversification.

PROJECT APPROACH

CH2M Hill worked mainly with local and oblast' government officials to

design and manage the programs. CH2M Hill consultants spent short periods

of time in Russia to design the project proposals and then returned to the

United States to complete the project design. Although USAID and CH2M Hill

established rapport with local and oblast' authorities in the affected

cities, the Ministry of Environmental Protection and Natural Resources was

only involved in the initial selection of project activities and their

locations. Subcontractors, U.S. nongovernmental organizations, and other

federal agencies helped implement parts of the project.

The project approach includes providing technical assistance,

demonstration projects, training seminars, and limited commodities.

Several components in both projects continued efforts initiated by the

U.S. Environmental Protection Agency, World Bank, and the City of

Pittsburgh.

CH2M Hill staff in Washington manage the project, and a regional director

and site managers in Russia handle the day-to-day activities and

coordinate with other implementers. CH2M Hill plans to hire and train

Russian employees who can eventually manage the activities without

assistance from its U.S. office.

CONTRACTOR PERFORMANCE

Project progress to date has been mixed. CH2M Hill met the requirements

of its core contract by establishing field offices, monitoring project

implementation, and providing support functions to its field staff. Even

though it has made some progress toward addressing the Novokuznetsk

project objectives, it has been slow to implement the Far East project.

CH2M Hill has missed critical milestones for both projects.

In Novokuznetsk, CH2M Hill established an air pollution database for the

180 heating plants in the city and developed a strategic plan to address

particulate pollution from the heating plants. It also upgraded the

city's air pollution program, trained Russian counterparts in

environmental auditing, and completed environmental audits of two large

steel mills. CH2M Hill is currently assessing local water monitoring

activities and has recommended laboratory improvements to more accurately

measure the quality of drinking water. CH2M Hill is working with the

Novokuznetsk Development Fund and local government officials to develop a

strategic plan. However, CH2M Hill has not provided an acceptable work

plan, which was due on November 30, 1994. The current work is based on

the delivery order specifications.

In the Far East project, CH2M Hill has been even slower getting started

and, according to USAID and Russian officials, had produced almost no

quantifiable results as of February 1995. Several factors have hindered

the project's implementation, including its increased complexity; the size

of the geographic area; and the large numbers of governmental officials,

local interest groups, and subcontractors involved. The project covers 2

large regions and will involve at least 16 implementing organizations,

including 2 U.S. federal agencies, subcontractors, and U.S.

nongovernmental organizations.

Several problems have delayed the effective implementation of both CH2M

Hill projects. One problem was that CH2M Hill experienced problems

filling critical staffing positions in Washington and Moscow and at the

field office level. Although the core contract was awarded in September

1993, the regional director did not arrive in Moscow until February 1994.

Other positions in Moscow funded in September 1994 delivery orders were

still being filled as of January 1995. The contract to implement field

support functions in Novokuznetsk and the Far East was awarded in April

1994, but on-site managers did not arrive until September and October

1994, respectively. The Far East project manager position was authorized

in September 1994, but the manager did not move to Russia until February

1995. CH2M Hill officials had difficulty finding qualified staff who were

willing to relocate to these areas because of the acute environmental

problems and remote locations. USAID and CH2M Hill officials agreed that

the on-site presence is essential for making progress. USAID-Moscow

officials said staffing delays and delays in producing an acceptable work

plan have hurt the credibility of the program in the region.

CH2M Hill also had difficulty developing acceptable work plans that define

how and when the scope of work will be implemented. CH2M Hill was

required to submit the work plans for both the Novokuznetsk and the Far

East projects within 60 days after signing the contract on September 30,

1994. USAID approved the work plan for the Far East project on May 8,

1995, but the work plan for the Novokuznetsk project was still being

revised as of June 1, 1995. According to an USAID official, the work

plans originally submitted were incomplete and lacked specific indicators

or other factors necessary to evaluate the activities.

Additionally, USAID officials said CH2M Hill had done a poor job of

providing them with the appropriate reporting documents for these

activities. USAID expressed concern over CH2M Hill's failure to provide

timely delivery of tracking materials, such as monthly summaries of

financial status by project, monthly presentations of progress on select

tasks, and weekly briefings on overall project progress. According to

USAID officials, CH2M Hill addressed their concerns and has recently

improved its reporting.

RESULTS

As of February 1995, the CH2M Hill projects had contributed little to

systemic reforms, and they will not generally be sustainable without

outside funding support. This limited contribution is due largely to the

vast environmental needs in Russia and the massive amounts of capital

investment needed to modernize or purchase equipment for restructuring

Russia's environmental sector. Also, USAID and CH2M Hill officials said

that Russian monitoring and enforcement procedures will be extremely

difficult to change and are not addressed in these projects. Finally, the

Ministry of Environmental Protection and Natural Resources was not

involved in designing the project, thus reducing the likelihood the

project could be duplicated on a wider scale. USAID officials said the

project will attempt to address systemic reform through efforts to

maintain and restock the forestry base.

Some components of the Novokuznetsk project are likely to address

environmental sector restructuring. CH2M Hill expects to work with

Novokuznetsk's industry, citizens, and local government to develop a

strategic plan and provide recommendations for creating an environmentally

safe city by 2010. However, these recommendations could require large

capital investments. For example, CH2M Hill recently conducted industrial

audits for two steel companies. After spending 6 weeks and using 7 U.S.

advisers and 25 Russian counterparts to conduct the audits, company

officials said the audits did not provide any new information on major

pollution sources. Further, the companies do not have the funding to make

the recommended improvements and will have difficulty obtaining it.

According to one steel mill executive, the environmental audit allowed the

mill to fulfill a condition for a World Bank loan. The Novokuznetsk

project places a considerable emphasis on the contractor delivering

studies and does not establish any indicators to measure progress in

reducing actual pollution.

Some components of the Far East project are designed to address the

region's need to maintain and restock its important forestry base. Efforts

are planned to (1) strengthen polices and develop an adequate

environmental regulatory structure, (2) create economic and political

incentives to use resources efficiently, (3) increase the participation of

nongovernmental agencies in environmental decision-making, (4) promote

U.S.-Russian partnerships, (5) promote the export of timber products made

by Russian workers, and (6) conserve biodiversity.

USAID MANAGEMENT

USAID's decision to use a core contract and delivery orders has caused

delays and excessive paperwork reviews for both CH2M Hill and USAID staff.

Under this system, USAID must prepare delivery orders and CH2M Hill must

submit detailed work plans for each project component within 60 days. The

decision to expand the Far East program has also delayed project design

and implementation. The expansion covers a larger geographic region and

greatly increased the scope of work, including the number of activities

and subcontractors involved.

The division of responsibility between USAID-Washington and USAID-Moscow

has affected the agency's ability to manage the project. USAID-Washington

maintains overall management authority, but has given USAID-Moscow

increased monitoring and program responsibility. However, USAID-Moscow

officials said they still had minimal authority to manage the project or

make changes. USAID-Washington must approve all program decisions,

including minor ones, such as country clearances for visitors and all

purchases exceeding $500. In April 1995, USAID-Moscow submitted an

initial request, which remained under review as of June 1, 1995, for

delegation of authority to the field.

USAID has had difficulty monitoring the projects. USAID staff said they

have not regularly visited the project sites because of the difficulty of

traveling to the sites and the lack of adequate staff. The USAID-Moscow

project officer keeps apprised of the project activities primarily by

talking to project staff over the telephone or in informal meetings and by

reviewing reports by the contractor or visiting teams.

DISTRICT HEATING--RCG-HAGGLER BAILLY

The district heating project is one component of USAID's Energy Efficiency

and Market Reform Project for the NIS. The project began in January 1992

and is considered the first economic development effort undertaken by the

United States in the region. With $5.3 million in funding, the project

was designed to improve district heating systems in six countries:

Armenia, Belarus, Kazakstan, Kyrgyzstan, Russia, and Ukraine.

Although the contractor, RCG-Haggler Bailly (RCG-HB), met most of its

objectives, we found no indication that the project was having a

significant impact on the sector. Most of the Russian work was

concentrated in two Russian cities, Yekaterinburg and Kostroma, and the

project was not completed in Yekaterinburg. Because USAID did not

adequately monitor the project, it was unaware of (1) problems that

prevented the completion of the project and (2) any long-term benefits, if

any, to the beneficiaries. An evaluation conducted by a consultant did

not identify obvious problems, and USAID did not address the

recommendations in this evaluation.

RCG-Haggler Bailly, one of three contractors implementing the district

heating project in the NIS, is an international management consulting firm

that specializes in energy and the environment.

SECTOR PROBLEM

Fuel and energy are an important part of Russia's economy. The subsidies

provided by the former Soviet government to Russian energy consumers, both

residential and industrial, created artificially low prices and promoted

the inefficient use of highly polluting energy. Since the dissolution of

the Soviet Union, Russia has implemented several policies, including

increasing or freeing coal, oil, and gas prices, to reform its energy

sector. Although still below world market levels, the cost of domestic

oil and oil products in Russia doubled in 1993 and 1994. Such increases

in energy prices have a significant influence on inflation and social

conditions. As energy prices increase, consumers must find ways to use

energy more efficiently.

The information in this section was obtained primarily from papers

presented at the International Energy Agency's October 1994 Symposium on

Russia's Energy Strategy and the Agency's report, Russian Energy Prices,

Taxes, and Costs, 1993.

PROJECT OBJECTIVES

In February 1992, RCGHB was awarded a contract for $550,000 to complete

the project in Russia. The project was amended in August 1992, increasing

the total cost to $1.3 million. The project had five objectives: (1)

foster improved management of energy use in heating plants by identifying

and implementing cost-effective "low cost-no cost" energy efficiency

improvements; (2) transfer energy auditing and management techniques,

including financial and economic analysis techniques; (3) provide

equipment support to implement low-cost options, improve monitoring and

energy management, and identify additional energy efficiency

opportunities; (4) support the World Bank's efforts to reform Russia's

energy pricing policies; and (5) promote the emergence of an energy

efficiency industry in Russia.

PROJECT APPROACH

RCG-HB and USAID worked with representatives from the Russian Ministry of

Fuel and Power, the Commission for Humanitarian and Technical Assistance

of the Russian Federation, nongovernmental organizations concerned with

energy efficiency and conservation, municipal governments, and industrial

enterprises.

The two primary Russian cities selected for the project were Yekaterinburg

and Kostroma. In these cities, extensive energy audits were conducted of

the district heating facilities, and three sites (i.e., hospitals,

apartment buildings, and heating plants) in each city were selected as

demonstration sites for U.S. energy efficiency equipment, including flow

meters, temperature sensors, and thermostatic control valves. The value

of the equipment supplied to the demonstration sites was approximately

$172,000. The project sites were intended to demonstrate the savings in

using no-cost or low-cost technologies and also serve to promote

American-made equipment.

In addition, RCG-HB conducted energy audit training seminars and provided

energy audit equipment to technicians in Yekaterinburg, Kostroma, Irkutsk,

Moscow, Murmansk, and St. Petersburg. To complete its work, RCGHB

contacted more than 250 U.S. equipment manufacturers to determine their

interest in conducting business in Russia. The 12 companies that

responded participated (at their own expense) in "wrap-up" seminars in

four Russian cities when the project ended. The information obtained at

these seminars was published in a lessons learned document.

CONTRACTOR PERFORMANCE

RCG-HB completed most of the objectives stipulated in its contract. The

products delivered to complete the objectives included energy audits in

two cities, energy audit training and distribution of energy audit

equipment, a study of natural gas pricing in Russia, and an energy

efficiency industry development effort. It also produced a video about

the project that was shown on Russian television.

RCG-HB was also required to identify, purchase, and install low-cost

energy efficiency equipment manufactured by U.S. companies. RCG-HB

purchased this equipment; however, due to problems with local conditions,

some of the equipment was not installed in Yekaterinburg. An RCG-HB

official said that in June 1993, a Russian subcontractor assured RCG-HB

that it would install the equipment in Yekaterinburg by the end of 1993.

We visited three sites in Yekaterinburg in February 1995 and found all the

equipment at one site was still in shipping containers. Russian officials

said the equipment at the other two sites only began operating in

September 1994 and January 1995, respectively. According to an RCG-HB

official, the company had not paid the subcontractor and would not pay

until the installation was completed. However, USAID had already paid for

the equipment, valued at $8,000.

Officials in Yekaterinburg stated that the equipment had not been

installed in 1993 for two reasons. First, in two cases, the sites (a

hospital and an apartment building) were under construction and the

construction plans had to be altered to accommodate the equipment. Second,

at the other installation site (a district heating facility), the

equipment had not been installed, and most likely will not be installed,

because the proper Russian authorities had not certified it. Officials in

Yekaterinburg stated that it would be illegal to install and operate the

equipment before it was certified. They explained that although the

equipment can be used for demonstration purposes at consumer locations

(e.g., apartment buildings), a public utility cannot use the equipment and

the information (e.g., energy consumption data) it produces as a basis for

charging customers.

Similar equipment was installed in Kostroma, according to USAID and RCGHB

officials, even though it had not been certified. USAID officials told us

that city officials were willing to install the equipment because they

realized the potential benefits.

RESULTS

We found no indication that the project had contributed to systemic reform

in the area of energy efficiency. Most of the work was concentrated in

two cities, and the project was not completed in either city. In

addition, USAID did not adequately monitor the project and could not be

certain of any long-term benefits.

USAID MANAGEMENT

USAID used an independent consultant, Management Systems International, to

evaluate the NIS district heating project, including RCG-HB's work in

Russia. The evaluation, published in July 1993, reported no serious

problems and declared the project a success. Specifically, the study

indicated that total equipment costs for the four cities in Russia

amounted to $418,000 and would produce an annual savings of $1.4 million.

It also noted that the equipment would reduce pollution. Furthermore, as

a result of the energy efficiency industry development effort, 12 U.S.

companies had sent representatives to the various countries to participate

in seminars held at the end of the project.

We found that the consultant's evaluation was deficient. The evaluation

did not mention the equipment installation problems in Yekaterinburg or

the need to have foreign equipment certified by the Russian government.

Instead, the evaluation stated that "by April 1993, all of the equipment

was installed and operating." In addition, USAID did not specifically

direct Management Systems International to assess the products RCGB was

required to produce, such as the natural gas pricing study for Russia or

the lessons learned from the energy efficiency industry development

effort. The evaluation did not discuss the quality of either of these

products. USAID officials stated that the natural gas pricing study had

been completed in a collaborative effort with the World Bank, which used

it in its work pertaining to loans made to Russia's natural gas sector.

However, the consultant's report contradicted USAID's statement by noting

that the World Bank did not make a serious attempt to involve RCG-HB in

its work in Russia.

Finally, the evaluation did not discuss the training seminars conducted by

RCG-HB in Irkutsk, Moscow, Murmansk, and St. Petersburg, or the energy

audit kit instrumentation supplied to technicians in these cities. The

continued use of these deliverables is an important factor to consider

when evaluating the success and sustained benefits of this project.

USAID officials were not aware of the problems we identified in

Yekaterinburg nor the shortcomings of the evaluation. They stated that in

June 1993, an official from USAID-Washington visited all the NIS sites

except Yekaterinburg. They stated that equipment had been installed at

the sites visited. A local national employee from the USAID mission in

Moscow also visited Yekaterinburg in June 1993 but did not report any

problems at that site. USAID officials discovered the problems we found

when they accompanied us to Yekaterinburg. USAID said it would take

corrective action.

Also, USAID has no mechanism to monitor various outcomes of the project,

including (1) the success of U.S. industry in entering the NIS market,

(2) policy reforms written into law, and (3) the rate of adoption of new

technologies. Although USAID said that the installed equipment would

produce annual savings at project sites, it did not record these savings

during the 1993 or 1994 heating seasons. Furthermore, USAID had not

determined the savings generated by either the energy audit kits provided

to technicians in six cities or the energy audits conducted in

Yekaterinburg or Kostroma.

USAID paid $18,385 for this evaluation.

HEALTH CARE TRAINING--PARTNERS FOR INTERNATIONAL EDUCATION AND

TRAINING

USAID initiated the NIS Exchange and Training program in the spring of

1993 to train NIS leaders about free-market economies and democratic

governance. USAID hoped that training the participants in the United

States would provide them with the technical skills and attitudes required

to create similar policies, programs, and institutions in their own

nations. We reviewed the health care training provided to Russians in

late 1993.

Our analysis indicated that the health care training had little likelihood

of contributing to systemic reform and that USAID now considers the

training to be irrelevant after Russia changed its direction for health

care reform. The training's primary objective--to facilitate Russia's

transformation to a democratic free-market system--was unrealistic for a

2-week training course. USAID did not follow up with participants to

determine the training's impact on systemic reforms. Although USAID

officials said that most participants have been involved in follow-on

projects, only 25 percent are slated for follow-on activities planned in

1995 and 1996.

SECTOR PROBLEMS

According to USAID, Russia's health care industry has a number of

problems. These problems include the virtual collapse of the

pharmaceutical and medical supply industry, poor quality of care due to

training and technical gaps, serious funding shortfalls, and a centralized

system devoid of incentives for efficiency and cost control. Although

Russian policies have produced an educated workforce with more doctors per

capita than the United States, the workforce lacks many of the basic

skills and institutions necessary to function in a democratic, free-market

context.

PROJECT OBJECTIVES

USAID contracted in June 1993 with its worldwide training support

contractor, Partners for International Education and Training (PIET), to

conduct training in the United States for 200 NIS leaders and

professionals at a cost of $2.6 million. The training objectives were to

facilitate the region's rapid and sustainable transformation from

authoritarian, centrally controlled regimes to pluralistic, democratic

countries with free-market economies;

provide participants with new skills and knowledge to contribute to

economic and social development;

promote the value of democratic decision-making;

provide an understanding of U.S. programs; and

lead to long-term relationships with U.S. institutions.

USAID also hoped that participants would share their new skills and

perceptions with their counterparts.

PROJECT APPROACH

Under the PIET contract, USAID missions identified the training topics and

selected the participants. USAID-Moscow selected the participants based

on their positions in oblast' health care systems and their planned

inclusion in follow-on projects. According to USAID, participants went to

the United States before participating in follow-on projects so they would

be more receptive to reforms. The training project encouraged missions to

link training, if appropriate, to ongoing or planned developmental

assistance by USAID and others.

After course topics and participants were selected, PIET was expected to

arrange training courses in the United States and provide administrative

and logistical support for international travel, living expenses, medical

insurance, tuition, books, and other needs. PIET was also expected to (1)

ensure that training programs at U.S. training institutions were

functioning properly, (2) monitor the participants' progress, (3) provide

USAID status reports, and (4) evaluate each training program.

CONTRACTOR PERFORMANCE

PIET subcontracted with Management Sciences for Health to provide the

training in the United States; 42 Russians were trained in health finance

and 20 were trained in pharmaceutical management. USAID subsequently

contracted with the Academy for Educational Development to make training

arrangements.

PIET met its contractual requirements by providing training,

transportation, and logistics, according to USAID officials. The

participants we spoke with in Russia praised PIET's support and assistance

as well as the quality of the training they received in the United States.

Our review of sample course assessments showed that other participants

generally gave high marks to the training. For example, in the evaluation

conducted by the USAID mission, most participants were satisfied with the

course and believed it was applicable to their work conditions.

PIET also met its monitoring and reporting requirements. PIET maintained

contact with the training institutions, called a random sample of

participants once a week, contacted the trainers on an as needed basis,

and helped participants with general adjustment problems. PIET also

provided all the required reports, including regular status reports and

course assessments. USAID-Washington officials were satisfied with the

quality of PIET's support and monitoring during the training.

RESULTS

USAID was unable to provide any evidence that the training will help

Russia's democratic or economic transformation. Although the training may

have met some secondary goals, without follow-on activities, fulfilling

these objectives will not likely result in systemic reform.

USAID-Washington officials agreed that the training could not meet all of

the contract's objectives. They said that a 2-week training course could

only "facilitate" reaching these objectives but not actually attain them.

Further, they provided the training quickly as a political imperative to

respond to the opening in the NIS, and they recognized training alone has

limited usefulness.

USAID was unable to substantiate that any of the 62 participants

contributed to any reforms, partly because the participants lacked the

authority, expertise, or resources to influence reforms. However, the

participants who had taken PIET health-related courses said the training

helped them understand U.S. programs and they had shared their training

with others.

USAID officials in Moscow and Washington said that training alone would

not influence systemic change and that subsequent training was better

integrated into follow-on activities. They said that the main purpose of

the PIET training was to make participants receptive to follow-on reform

projects, which USAID thought would occur. However, USAID later dropped

plans for follow-on activities in Central Russia because the oblasts were

not reform-minded and the contractor reported that only 25 percent of the

Siberian participants would participate in follow-on activities.

The Russians did not see health reform as a priority when the early

training took place, and Russia has only recently begun to consider the

direction of reforms, according to USAID-Washington officials. Further,

this early training is now irrelevant because it was based on Russian

policy directions that were later discarded as unworkable.

USAID MANAGEMENT

The mission was forced to move much more quickly than it desired because

it was under extreme congressional pressure to quickly establish the

training program, according to USAID officials. As a result, the health

care training was initiated before it could be integrated into follow-on

projects more likely to facilitate systemic change. Further, because the

Russians were unclear about what reforms they wanted, the mission had

trouble targeting the training. The Russian officials began exploring

reform options with the mission in December 1994.

USAID-Moscow officials assessed the training after participants returned

to Moscow; however, they have had no contact with the participants since

then. They did not know which participants, if any, would be involved in

any of the follow-on activities planned in Siberia.

COMMERCIAL REAL ESTATE--INTERNATIONAL BUSINESS & TECHNICAL CONSULTANTS, INC.

The International Business & Technical Consultants, Inc. (IBTCI) project

did not achieve its goal to increase the availability of commercial real

estate to small enterprises, although it did provide potentially useful

technical assistance in three cities. The project did not contribute to

systemic reform and was not sustainable. IBTCI did not replicate the

pilot project--a project objective--in part because the roll-out cities

were poorly chosen. IBTCI was responsible for choosing appropriate

cities, but its short-term consultants lacked sufficient knowledge of

Russia and local conditions to determine what cities would have

cooperative officials and could benefit from the project.

SECTOR PROBLEM

Much of Russia's commercial real estate is still owned by the government.

Rather than divesting its ownership rights, the central government has

decentralized those rights to local governments, both regional and

municipal. Although this practice is quite common among other countries

in transition, Russia is different because local governments (1) have a

virtual monopoly on commercial real estate and (2) have not moved toward

commercial real estate leasing using market mechanisms. Highly

inefficient users occupy valuable commercial space, contributing very

little to local budgets, while private sector development is blocked by

the unavailability of property.

Harding, April L., Commercial Real Estate Market Development, The World

Bank, Discussion Paper Number 109 (May 10, 1995).

PROJECT OBJECTIVES

USAID and GKI recognized this problem and signed a task order with IBTCI

to develop a solution. The $2-million task order for the rapid diagnosis

pilot project and roll-out project was part of IBTCI's $13.3-million

omnibus contract. The initial deadline of May 1994 was extended to

December 1994, but without any increase in the cost or level of effort

required. The general purpose of the task order was to significantly

increase the availability of commercial property in Russian cities.

The specific goals of the task order were to examine the causes of limited

access to retail space, implement a pilot project in a selected city, and

then replicate the pilot project in other oblasts. IBTCI was to (1)

deliver a report on the root causes of and solutions to the problem of

commercial property access for one city; (2) design an implementation plan

to address these issues, including procedural, legal, administrative,

financial, policy, and other measures; (3) replicate the pilot project in

at least five other oblasts; and (4) produce and nationally distribute

publicity and instructional materials for local state property committees,

local authorities, and entrepreneurs on how to increase the availability

of retail property.

PROJECT APPROACH

IBTCI used a subcontractor, Boston Consulting Group (BCG), to perform the

rapid diagnosis phase and conduct the pilot project in the City of Perm'.

The goals of the pilot project were to (1) design and test a method for

increasing the amount of commercial real estate available to small and

start-up businesses and (2) identify any constraints or impediments that

might exist. The pilot was intended to serve as a model for instituting

the program in five other Russian cities. IBTCI instituted the roll-out

in Irkutsk, Tver', Novgorod, Yekaterinburg, and Vladivostok.

Because it had previously worked in Perm', BCG used staff who already had

a relationship with municipal officials when it began the diagnosis and

pilot phases of the project. In contrast, IBTCI relied on consultants who

made short visits to the other cities to research, plan, and implement the

roll-out.

During the rapid diagnosis phase in Perm', BCG identified three feasible

ways of improving access to commercial space: convert residential

premises to commercial use, develop a secondary real estate market, and

optimize the leasing process. BCG, IBTCI, USAID, and GKI selected the

leasing optimization method because they thought some concrete results

were possible during the study period, even though it was predicted that

this alternative would have limited support and low potential impact.

Lease optimization means, among other things, (1) moving toward

market-determined rents, (2) removing bureaucratic discretion in space

allocation, and (3) creating incentives to sublease unused space.

Perm', with a population of 1.5 million, was selected for the pilot

because of its intermediate size and presumed representative nature of

municipalities within the Russian Federation.

CONTRACTOR PERFORMANCE

BCG conducted the rapid diagnosis and pilot phase of the project from

November 1993 to March 1994 in Perm'. BCG devised a two-track auction

system for making municipality-controlled real estate available to private

businesses. The first track was an auction for the right to lease

specific commercial real estate properties (i.e., a one-time premium).

The second track was an auction for the rental rate at which a property

would be leased. The purpose of this system was to introduce market

mechanisms into the allocation and pricing of commercial real estate.

Under this system, bidding for the right to lease and the rent to be paid

replaced government bureaucrats with market mechanisms.

The results of the first auction, which occurred on March 1, 1994, were

not promising. In the first track auction, three properties were

available. The right to lease them was sold for each property. In the

second track auction, 15 properties, all basements, were available. Bids

were made on only 3 of the 15, and each received only one bid. The rental

rate for the three properties did not exceed the rent that started the

bidding.

The results of a second round of auctions, which occurred in May 1994,

were also disappointing. In the first track auction, 10 properties were

available, but the right to lease was sold for only 4 properties, although

several parties bid on them. In the second track auction, three

properties were available, but only one received a bid, and that was the

starting bid. These results were not perceived to have significantly

increased the amount of commercial real estate available in Perm'.

IBTCI started work on the roll-out in mid-February, before the Perm' pilot

was completed or its results evaluated. IBTCI soon found that none of the

five cities chosen for the roll-out had conditions that approximated, let

alone duplicated, those in Perm'. The roll-out cities seem to have been

chosen more for their geographic and population distributions than for any

existing economic, political, and regulatory conditions that might make

the Perm' model replicable. Because of these differences, IBTCI had to

deviate from the Perm' model and basically develop five new pilot

projects; nonetheless, it still experienced problems.

Irkutsk officials were not cooperative with IBTCI and declared the

information needed to assess the commercial real estate situation a state

secret. Local officials were not ready to participate in the project.

In Tver', an auction system had been functioning between June 1992 and

December 1993. The original investment tender process used in the auction

was challenged in court and hopelessly compromised. IBTCI introduced a new

tender process in Tver', but the new system's effectiveness has not yet

been demonstrated.

The Novgorod officials opposed conducting right-to-lease auctions because

they feared losing future revenue and the city had experienced poor

results from a similar auction in November 1993. IBTCI focused on

establishing a market for municipal, oblast', and private commercial space

by creating a real estate listing center, developing a secondary market,

and encouraging officials to allow increased and legalized subletting.

The listing center's effectiveness has not yet been demonstrated.

In Yekaterinburg, an effective auction system has been in place since

1992. City officials were not interested in IBTCI's original task of

increasing the use of commercial leases. Instead, they wanted assistance

in how to use retail and commercial space efficiently and increase the

city's revenues from property leases. Although IBTCI submitted some

analyses and recommendations addressing their concerns, city officials

told us that IBTCI came to town on different occasions, spent little time

there, did not speak to the appropriate local officials, and presented an

academic report that was of little use to them.

Vladivostok city officials were interested in privatizing commercial real

estate, but were unable to devise a method that would use mortgages to

provide substantial revenue for the city. IBTCI devised a mortgage

instrument that allowed the city to continue receiving income by holding

the mortgages and allowed small business owners to bid for a property and

provide as little as 5 percent of the final cost as a down payment. The

city auctioned one property in August 1994 for under $7,000, but local

officials doubted they would use an auction again because the city did not

not have any more excess property.

By the time IBTCI had completed its work in the five cities, none of

the cities had participated in any activities that remotely resembled

the Perm' model. As a result, the objective of replicating the pilot

project in other cities was not achieved.

There were various reasons for IBTCI's inability to replicate the Perm'

model. First, tensions between IBTCI and BCG caused some problems. BCG

performed both the rapid diagnosis and the pilot phases, but IBTCI

determined that BCG's approach was not adequate. Russian officials

monitoring the project were aware of tensions between IBTCI and BCG early

in the project, but IBTCI was obligated to fulfill the contract and

replicate the model. The tensions between IBTCI and BCG resulted in

little continuity of personnel from the pilot to the roll-out phases.

Second, a provision of Russia's 1994 State Privatization Program Act and

its implementing regulations caused problems in the Perm' pilot. The

provision gave lessees who obtained their leases competitively (i.e., at

an auction) the right to buy the property at the end of the leases. The

implementing regulation set an extremely low selling price for such

privatized properties. IBTCI said that the act's provision and the

implementing regulation stopped the Perm' model because city officials did

not want to lose revenue from leases and did not want to be forced to sell

leased property for extremely low prices. Even though reports identified

the problem as early as January 1994, USAID, GKI, and the Russian

Privatization Center took no effective action to address the issue.

Third, although officials at the federal level agreed earlier that the

project should be done and that the Perm' model was viable, local

officials in the roll-out cities did not agree with the Perm' model or its

usefulness in their cities.

Fourth, although the consultants used by IBTCI for this project had some

experience in Russia and some spoke Russian, Russian authorities

questioned the level of some IBTCI consultants' professional experience.

In addition, the consultants did not have enough knowledge of the Russian

localities and local politics to choose roll-out cities well. IBTCI staff

did not reside in the cities during the roll-out. Instead, they would fly

in, do a few days work, then leave. Thus, they were unable to identify

what cities would be the best candidates for replicating the Perm' model.

Even BCG had problems carrying out a successful pilot, despite its

knowledge of and relationships in Perm'.

Novgorod and Tver' were included because they are relatively small cities,

under 250,000 in population. Irkutsk and Vladivostok represented

medium-sized cities, with populations between 250,000 and 750,000.

Yekaterinburg was to represent large cities, population over 750,000, and

be a match for Perm'.

RESULTS

The project was not sustainable and did not contribute to systemic reform.

Although IBTCI's final report provided solutions to specific problems, the

project did not implement the pilot or develop a method that could be

replicated in other cities. USAID officials and the Russians who were in

charge of disseminating the report did not know whether or where the IBTCI

"solutions" had been applied in any but the six cities. City officials we

interviewed in Yekaterinburg and Vladivostok were not using the concepts

of the project.

GKI and the Russian Privatization Center had originally proposed the

project, which suppported a federal initiative. However, an existing GKI

act and its implementing regulation potentially forced local governments

to sell leased property at low prices to anyone who bought the lease at an

auction. This regulation contributed to the poor results of the project.

USAID MANAGEMENT

USAID managed this project from Washington with limited help from

Go to TOP of this page


RETURN to Palms' Lobby RETURN TO HOME PAGE




Palms & Company, Inc., Investment Bankers (1934-1997): Palms Palms Bayshore Building, 6421 Lake Washington Boluevard Northeast, Kirkland, (Seattle), State of Washington, United States of America, 98033-6876;
http://www.peterpalms.com
Phone: 1-425-828-6774 & 1-425-827-5528
Copyright 1995, Palms and Company, Inc.; all rights reserved; email: palms@PeterPalms.com
Date Last Revised: Sept. 10, 1997