Palms & Company Document


WHAT'S NEW ----- About The Portal To Russia ----- Email Dr. Palms




Foreign Assistance: Assessment of Selected USAID Projects in Russia

(Letter Report, 08-03-95, GAO-NSIAD-95-156).

PART IV

THIS DOCUMENT IS IN FOUR PARTS. THIS IS PART IV

CLICK FOR PART I, PART II, PART III, PART IV

USAID-Moscow, jointly with GKI and the Russian Privatization Center; it

relied on consultants from the Harvard Institute for International

Development and the Center to help monitor the project. Nonetheless,

USAID did not monitor the project adequately. Even though IBTCI filed the

required reports, these reports failed to describe how much the roll-out

deviated from the Perm' model. Center officials said they first became

aware that the pilot was not being implemented in other cities in late May

1994, long after the roll-out could be redirected to other cities.

When problems were known in some cases, USAID did not take any corrective

action. For example, a Harvard consultant who visited some sites raised

questions about the cities selected for the roll-out, but USAID took no

corrective action. Similarly, the problem with the State Privatization

Program Act and its implementing regulations was mentioned in reports in

January 1994, but no action was taken to resolve it. Finally, USAID

officials said they were aware of the tensions between BCG and IBTCI, but

simply told IBTCI to work the problem out themselves. USAID-Moscow

officials said they did not have enough staff to intervene when problems

arose, visit the project sites, and talk with beneficiaries about how the

project was progressing.

AGRIBUSINESS PARTNERSHIPS PROJECT--TRI VALLEY GROWERS

The lack of quantifiable objectives or time frames in the Tri Valley

Growers' (TVG)21 project design makes it difficult to measure the

project's success. TVG helped to facilitate the work of two agribusiness

partnerships in Russia; nevertheless, USAID concluded that TVG did not

perform adequately. It is too early to determine the long-term economic

viability of the partnerships; however, the involvement of U.S. companies

increases the likelihood the partnerships will be maintained. The

partnerships will probably not have any measurable effect on Russia's

agricultural sector because of their limited size and number.

Tri Valley Growers is an agribusiness association based in California.

Its members are involved in value-added fruit and vegetable preserving,

processing, packaging, distribution, and marketing.

SECTOR PROBLEM

Agriculture plays an important role in the Russian economy. Although

estimates vary, Russia has approximately 27,000 large state and collective

farms, which cultivate approximately 90 percent of Russia's arable land.

Approximately 270,000 private farms cultivate 5 percent of the arable

land. The remaining 5 percent is made up of private garden plots. The

total farming population comprises about 26 percent of the country's

population. Subsidies and income transfers to the agricultural sector

represent 25 percent of Russia's public expenditures. Some of these

subsides could be expected to be eliminated if the agricultural sector

were privatized.

Russian agriculture is a low-productivity sector. For example, milk cows

and potato and grain crops yield about half of western levels, and labor

productivity is probably as low as one-tenth. In addition to low

productivity, Russia has been plagued by losses of up to 50 percent in its

storage and handling systems. Finally, Russia's food processing system

suffers from poor management and a lack of quality produce, additives,

ingredients, and packaging materials.

Although the Russian government has begun reforming the agricultural

sector, the actual transformation of farms and agribusiness enterprises

into market-oriented, productive entities is moving slowly. In 1992, it

reorganized state and collective farms and agricultural input and output

distribution enterprises into joint stock companies. However, most farms

have not altered their operations to increase productivity and

competitiveness.

This information was obtained primarily from the Rural Development

Institute's report, Agrarian Reform In Russia (May 1993); a report

produced by Chemonics International for USAID, Agriculture

Post-Privatization In Russia (Jan. 1994); and USAID project documents.

PROJECT OBJECTIVES

In August 1992, USAID developed the agribusiness partnerships project as

the cornerstone of its Food System Restructuring Project. The

agribusiness partnerships project was designed to create efficient systems

for providing inputs to agriculture and for processing and distributing

agricultural products. USAID intended to catalyze NIS private sector

activity by facilitating the involvement of private U.S. agribusinesses.

Between January and May 1993, USAID signed cooperative agreements with

three agribusiness cooperatives: Citizens Network for Foreign Affairs

(CNFA), TVG, and Agricultural Cooperative Development International. We

reviewed USAID's cooperative agreement with TVG, which had obligated $5.2

million for the region.

To achieve the project's objective, TVG was to facilitate partnerships

between American and NIS private agribusiness-related enterprises.

However, the agreement did not specify the number of partnerships or the

related time frames.

At the time of our review, USAID's Inspector General was reviewing the

cooperative agreement with CNFA.

The combined budget for the three cooperative agreements under the

agribusiness partnerships project was $59.3 million. As of February 1995,

$52.5 million had been obligated.

PROJECT APPROACH

TVG established an office in Moscow staffed by one American director and

three Russian nationals. This office was supported by several TVG

headquarters staff in California. The American director did not have an

agribusiness background but was responsible for managing the office,

identifying potential Russian and American agribusiness partners,

reviewing partnership proposals, and submitting the proposals to USAID for

final subgrant approval.

According to TVG officials, TVG identified potential Russian agribusiness

partners through a network of contacts at the Ministry of Agriculture,

Association of Individual Farms and Agricultural Cooperatives of Russia,

World Bank, European Bank for Reconstruction and Development, Peace Corps,

investment funds, and regional and local administrations. To identify

American partners, TVG canvassed its members in the United States,

advertised in agricultural publications, contacted agribusinesses via

telephone, and looked for firms already operating in Russia.

Once identified, TVG worked with the American and Russian partners to

develop proposals for USAID's approval. After receiving USAID approval,

TVG awarded subgrants to U.S. agribusinesses working in Russia primarily

to provide technical assistance and agricultural training to help create

efficient food systems. The American agribusiness partner was required to

provide at least 2.5 times the level of funding provided by USAID, to

ensure its commitment to the partnership and the long-term economic

viability and sustainability of the joint venture.

The items purchased with the USAID subgrants are referred to as

"additionality" components, or those components that might otherwise not

be included in the joint venture without USAID funding. Additionality

components include additional training and facility expansion.

CONTRACTOR PERFORMANCE

TVG established six partnerships in five NIS countries, with two in

Russia. As of March 1995, one additional partnership in Russia was

awaiting USAID approval. The first partnership established in Russia was

with Petoseed Company, Inc., and is located in Krasnodar. Petoseed

produces vegetable seeds that will be sold in the NIS and internationally.

During the 1994 growing season, Petoseed produced 11,000 pounds of seed in

Russia. The second TVG Russian partnership involves CTC Foods Company,

which is building a potato processing facility in Pushchino. If finished,

the facility will produce dried potato flakes that will be sold primarily

to hospitals and schools.

The two American agribusiness partners exceeded the required level of

partnership funding in both partnerships. Contributions by USAID, U.S.

agribusiness partners, and Russian beneficiaries to the TVG partnerships

in Russia are shown in table III.1.

Table III.1

Agribusiness Partnerships Established by

Tri Valley Growers in Russia

Su

bg

ra Russian

nt Total U.S. firm firm Grant U.S. firm

ee partnership USAID grant share share\a expended expended

Pe $1,085,975 $309,250 $776,725 0 $44,054 $181,338

t

o

s

e

e

d

CT 4,300,000 800,000 2,200,000 $1,300,000 428,249 1,624,789

C

F

o

o

d

s

To $5,385,975 $1,109,250 $2,976,725 $1,300,000 $472,303 $1,806,127

t

a

l

a The Russian partners' contributions are generally in-kind

contributions.

Source: TVG statistics as of May 25, 1995.

TVG had difficulty identifying partnerships. TVG staff had difficulty

beginning work in Russia because of poor telecommunication and office

facilities, the chaotic Russian business environment, the limited number

of American firms willing to invest in Russia, limited funding, and a

small staff. According to a TVG official, Petoseed and CTC Foods

contacted TVG to participate in the project. However, both companies were

already working in Russia before USAID had established the agribusiness

project and located Russian partners on their own. He said they would

have invested in Russia without USAID involvement. An official at the

Association of Individual Farms and Agricultural Cooperatives of Russia

told us that the Association tried to work with TVG to identify Russian

partners but received only "empty promises."

Although USAID never specified the number of partnerships that it wanted

to establish within a given time frame, it concluded that TVG had not

performed adequately. Between May and December 1993, USAID expressed

concern about the number of partnership proposals TVG was submitting and

the quality of the proposals. A February 1995 USAID review of the

agribusiness project stated that TVG required more support by USAID staff

and was less committed to the project than CNFA. TVG closed its office in

Moscow in August 1994 and has stopped the Russia part of its program

because USAID terminated the agribusiness partnerships project in Russia.

Nevertheless, USAID's review noted that the partnerships to which TVG had

made subgrants were doing well. However, a TVG official told us in May

1995 that because of financial problems, CTC Foods may not be able to

continue its work in Russia. Consequently, the processing facility in

Pushchino may never be constructed. According to a USAID official, TVG's

Moldova office now monitors the Russian subgrants.

Petoseed also established seed production facilities in Ukraine and

Moldova through TVG.

RESULTS

The agribusiness partnerships developed by TVG in Russia have not been

operating long enough to adequately judge their impact. However, due to

their limited scope, it is unlikely that the partnerships will have a

significant effect on reforming Russia's agricultural sector.

USAID MANAGEMENT

USAID-Washington designed the agribusiness partnerships project in 1992,

before the USAID-Moscow mission was opened. USAID-Washington and

USAID-Moscow split the oversight responsibilities: Washington was

primarily responsible for TVG's compliance with the cooperative agreement

and Moscow was responsible for subgrant proposal evaluation. Final grant

approval was a joint Moscow-Washington effort.

Although USAID-Moscow raised continued concerns about the agribusiness

partnerships project's ability to influence systemic reform, the project

proceeded. USAID-Moscow officials called for a review of the project as

early as November 1993, and they developed a statement of work for an

evaluation team. However, USAID-Washington told USAID-Moscow to "forget

the assessment and get on with the job." Consequently, no assessment was

conducted. According to USAID officials, an evaluation is planned for

June 1995.

According to USAID officials, the agency wanted to implement the project

quickly and demonstrate results. TVG's Moscow director stated she was

pressured to submit proposals quickly because USAID was being pressured by

Congress. However, both CNFA and TVG officials complained that USAID's

subgrant approval process was arduous and lengthy. They said it took

several months for USAID to accept or reject a proposal and added that

USAID-Washington caused most of the delay. USAID-Washington officials

said the delays were caused by the time required to research legal issues,

conduct environmental audits, and work through the Washington bureaucracy.

The cooperative agreement with TVG called for quarterly program

performance reports and annual progress reports. An independent

accounting firm was to audit TVG's financial statements. Although USAID

officials said that TVG met all of its reporting requirements, our review

indicated that TVG had not submitted annual reports. According to USAID

officials responsible for the project in Russia, USAID staff visited only

half the project sites established by TVG, CNFA, and Agricultural

Cooperative Development International between May 1993 and November 1994.

USAID was required to annually assess the performance and program

direction of the cooperative agreement and contract for an independent

external evaluation. As of March 1995, it had done neither. However,

CNFA completed an evaluation of the agribusiness partnerships project in

August 1994 at USAID-Moscow's request. It reported that the project had

not started agribusiness partnerships quickly, had not made a significant

contribution to sectoral reform, and had little to show for the

"additionality" purchased with USAID funds. CNFA's internal evaluation

did not address TVG's performance. USAID completed an internal review in

February 1995, but the review did not cover the additionality components.

The review stated that it was unrealistic to expect the overall project to

have a significant, measurable impact on the food system in the NIS.

USAID has discontinued the agribusiness partnerships project in Russia

and, as of September 1994, stopped accepting proposals for Russian

agribusiness partnerships. In addition, USAID has decided not to obligate

any additional funds for the project. Agency officials stated that the

project itself cannot adequately address the obstacles of reforming the

agricultural sector and indicated that other projects, such as the

Russian-American Enterprise Fund, were better vehicles for financing joint

ventures.

OFFICER RESETTLEMENT HOUSING PILOT

The Russian officer resettlement pilot project has been successful in

providing the required housing units, although not within the original

time frames. The project's secondary objectives--to provide job skills

training for demobilized officers and to help facilitate housing sector

reform--were only partially met. By implementing a pilot program, USAID

was able to test the viability of a housing construction project and apply

lessons learned to the $160-million follow-on project.

Planning and Development Collaborative International (PADCO), the

contractor tasked to provide construction management services, was

successful in part because it (1) had experience in working on housing

sector reform in Russia, (2) established a physical presence in Moscow and

in the field, (3) obtained at least some buy-in and involvement from the

local Russian government, and (4) employed Russian staff to oversee

construction activities.

SECTOR PROBLEM

The Russian Ministry of Defense has traditionally provided qualifying

retired and demobilized military officers with a dwelling unit or plot of

land and some job skills training. After the Soviet Union dissolved,

between 200,000 and 350,000 officers needed housing; approximately 42,000

were located in the Baltic Republics of Estonia, Latvia, and Lithuania.

However, since the dissolution, the Russian government has lacked the

housing stock to resettle all the demobilized military officers. Further,

Russia's severe economic problems, housing shortages, and lack of "social

guarantees" for these retired officers has delayed troop withdrawals.

PROJECT OBJECTIVE

President Clinton announced the Russian officer resettlement program at

the Vancouver Summit in April 1993. Later, in July 1993, he stated at the

G-7 Heads of State meeting in Tokyo that the program should encourage

rapid withdrawal of demobilized Russian officers from the Baltic

Republics. The Russian Officer Resettlement Initiative is being conducted

in two phases--a $6-million pilot and a $160-million follow-on project.

The pilot's primary objective was to construct 450 housing units by July

1994 for the resettlement of demobilized Russian military officers. The

follow-on project was to provide up to 5,000 units (2,500 constructed and

2,500 voucher certificates) by November 30, 1996, for officers demobilized

in the Baltics or other countries outside Russia. The pilot project's

secondary objectives were to provide job skills training, experiment with

new housing technologies, assist private firms in housing development and

construction, and expand the scope of housing choices.

PROJECT APPROACH

To implement the pilot project, USAID contracted with PADCO for

construction management services. It also awarded fixed-price contracts

to five Russian builders and one private voluntary agency to construct

housing units in five cities. Finally, it provided a grant to the

International Catholic Migration Commission for training.

According to project officials, PADCO assisted the project design team

that included officials from USAIDWashington and USAID-Moscow. This team

visited potential project sites, evaluated projects, and negotiated

construction contracts. PADCO was responsible for managing the

construction activities and monitoring contractor performance. U.S.

officials said the design team created the pilot with only minimal input

from the Ministry of Defense or the Ministry of Construction. USAID

officials added that the design team conducted its own field assessment to

select participating cities and worked almost exclusively with the local

authorities in these cities. The local authorities were to provide

infrastructure services such as heating, water, and road access for the

housing units.

USAID relied on the Russian Ministry of Defense to select the officers to

receive the housing. The initial design for the pilot program did not

stipulate where the officers should come from, but as a result of the

Tokyo G-7 meetings in July 1993, USAID established criteria that gave

priority to demobilized officers living in the Baltics.

The criteria also included housing for officers from other areas outside

Russia because two cities were reluctant to provide infrastructure for

officers exclusively from the Baltics. Under this criteria, officers

demobilized in other areas would be included. USAID's compromise with

these cities allowed some demobilized officers from their own

jurisdictions to receive housing. In Nizhniy Novgorod, half the officers

could come from its jurisdiction, while in Volgograd, 40 percent of the

officers could come from its jurisdiction. USAID and PADCO officials said

beneficiary composition would also be an issue in the follow-on project.

PADCO's project staff established a long-term presence in Moscow and

traveled regularly to the various building sites. It also hired and

trained Russian construction specialists to supervise the construction in

each city. USAID officials said PADCO's experience in Russian housing

issues helped facilitate this project.

CONTRACTOR PERFORMANCE

PADCO and Russian contractors generally met the program's primary

objective of providing housing units, although not within established time

frames. As of July 1994, only 94 (21 percent) of the 452 units were

completed, although as of February 15, 1995, the project had provided 422

units (93 percent) through a combination of construction and voucher

certificate activities. (See table III.2 and figs. III.1 and III.2.)

Table III.2

Status of Russian Officer Resettlement Pilot Project as of February 15, 1995

Pending

Originally Added Completed completion Transferre

Location planned Terminated allotted issued approval d to owner

Construc

tion

Lipetsk 40 40

Nizhniy 128 128 45

Novgorod

1

Nizhniy 50 50 0

Novgorod

2

Novosibi 180 180 0

rsk

Tula 1 14 14 12

Tula 2 16 16 9

Tula 3 30 30 0

Volgogra 32 32 29

d 1

Volgogra 80 80 75

d 2

Volgogra 72 72 0

d 3

Subtotal 460 270 182 342 30 170

Voucher

certifi

cates

Novgorod 40 40 2 38

Pskov 40 40 2 38

Subtotal 80 80 4 76

Total 460 270 262 422 34 246

Figure III.1: Housing Units Built in Volgograd for Russian Officers

(See figure in printed edition.)

Figure III.2: Duplexes Built

in Tula for Russian Officers

(See figure in printed edition.)

Of the 10 project sites in 5 cities, USAID terminated 3: one because

newly elected local officials refused to meet the previous

administration's commitments to provide infrastructure support to the

housing units and 2 because contractors defaulted on their building

commitments.

In Novosibirsk, USAID and PADCO officials said federal and oblast'

officials were not involved in the initial agreements. Therefore, they

had no authority to require the local administration to abide by the

contract, and they would not allocate additional funds for the

infrastructure.

In Lipetsk, the contractor was a private voluntary agency that

subcontracted with a local Russian construction firm to execute the work.

When the subcontractor defaulted, the agency was unable to find a

replacement to complete the work. At the Nizhniy Novgorod 50-unit project

site, project officials said the Russian contractor ran into financial

problems and stopped work, claiming that the $8,500 per unit allowed in

the contract was not enough to cover costs. Although the city offered

several incentives, including a $300,000 letter of credit and land for

additional construction, USAID and PADCO officials said the contractor was

unwilling to spend his own funds and the contract was terminated by USAID.

USAID officials said the contractor at the 128-unit Nizhniy Novgorod site

was concerned that $8,500 per unit was not enough to cover the cost of

construction. The contractor had completed almost 70 percent of

construction when increased construction costs, caused by rapidly rising

inflation (9 percent a month) and the devaluation of the ruble, forced him

to stop work. According to USAID officials, because the contractor had

done a good job, used his own funds from other projects, and was

well-connected with city and oblast' officials, he negotiated an agreement

so that the oblast' and USAID would cover the increased costs of the 128

units. To ensure the project's completion, USAID and the oblast'

administration each provided an additional $700,000, thus increasing the

per unit price to $19,500.

Because contracts were terminated months after they were awarded, USAID

developed a method to meet the housing requirements quickly. It awarded a

contract to the Urban Institute to implement a voucher certificate

program, which allowed officers to purchase existing local housing in a

participating area or housing under construction. Because of increased

construction costs, the inclusion of land, and infrastructure costs, the

vouchers were increased from the $8,500 per unit in the construction

program to a maximum of $25,000 per unit. According to USAID officials,

using voucher certificates allowed the pilot program to provide housing

units much quicker than through direct construction. As of January 30,

1995, 80 vouchers had been disseminated to the officers, and 76 (95

percent) of the them had been used to purchase units, which were turned

over to the officers.

The International Catholic Migration Commission's efforts to address one

of the project's secondary goals of job skills training has shown limited

results, according to USAID housing officials. As of December 1994, it

had arranged training for 46 beneficiaries who attended business courses

in Pskov, Novgorod, and Volgograd. The USAID official said construction

delays and the subsequent delays in officers relocating to their

respective cities affected start-up activities. Further, the official

said the Commission did not adequately identify the officers' training

needs and failed to recognize that many of them were not interested in

training.

Project officials said only minimal progress was made in addressing other

secondary goals, such as demonstrating new housing technologies, expanding

customer choices, and implementing more stringent quality control

standards. For example, in Tula, contractors constructed 14-, 16-, and

30-unit duplexes, which took as long or longer to build than traditional

high rise structures. (See fig. III.2.) PADCO field representatives

worked with local builders to ensure that quality control measures were

introduced and achieved.

RESULTS

The officer resettlement pilot project accomplished its objective of

providing housing to demobilized officers. The project was not designed

to address systemic reform or to be sustainable, and it did not do so.

PADCO officials said the attempts to sustain the effects of the project's

secondary objectives were short-lived, although the lessons imparted by

PADCO--new housing technologies, housing choices, and quality control

measures-- may have some positive effect on the building industry and

contractors. USAID and Urban Institute officials said the lessons learned

from implementing the voucher certificate activity by the banks, realtors,

and local governments may be used to facilitate the local governments'

transition to a private housing market.

As a result of the pilot project, USAID incorporated the lessons learned

as it designed the $160-million follow-on initiative to provide 5,000

units to officers from the Baltics. The primary changes included (1)

obtaining total support, involvement, and buy-in from all three levels of

Russian government; (2) using the voucher certificate program to expedite

the relocation of 2,500 officers; (3) stipulating that a maximum of 10

percent of the demobilized officers could come from local jurisdictions;

(4) using a U.S. construction management firm as the prime construction

contractor and subcontract to the individual builders; (5) using only

experienced, well-connected Russian builders; (6) selecting partially

completed buildings and sites with existing infrastructure; (7) using a

traditional Russian housing design; and (8) providing a more realistic per

unit cost ($25,000 versus $8,500). According to USAID officials, these

changes are expected to allow the follow-on project to proceed more

quickly and efficiently than the pilot.

USAID MANAGEMENT

USAID-Moscow had management responsibility for the project and generally

did a good job of managing, monitoring, and overseeing it and coordinating

with USAID-Washington. PADCO officials said USAID-Moscow actively

assisted the contractors in reaching acceptable compromises with

government officials and contractors. The USAID-Moscow project team

reviewed project status reports, visited project sites, and held regular

meetings with contractors. Finally, AID terminated work when problems

could not be overcome.

(See figure in printed edition.)Appendix IV

COMMENTS FROM THE U.S. AGENCY FOR

INTERNATIONAL DEVELOPMENT

(See figure in printed edition.)

The following are GAO's comments on USAID's letter dated June 1,

1995.

GAO'S COMMENTS

1. We have incorporated these comments into the report where

appropriate.

2. Although we noted project shortcomings, we also recognized the

contribution Deloitte & Touche made toward the privatization process and

considered the project a success. Moreover, we recognized USAID's

positive contribution to the overall privatization effort.

3. We conducted a detailed review of Tri Valley Growers' performance, one

of the three contractors responsible for implementing the agribusiness

partnerships project, to determine whether this expenditure of funds had

any sustainable impact. We concluded that it did not. Although we did

not draw any conclusions about the agribusiness partnerships project as a

whole, our analysis casts doubt on whether the project can have a systemic

impact if the individual partnerships are not having an impact. (See

comments 29 and 30 for additional discussion.)

4. It is too early to know whether USAID's prediction concerning the

outcome of ongoing activities in the energy sector will result in

significant sector reform. Many of these projects are just starting and

must overcome many obstacles. For example, in our September 1994 report

on nuclear safety, we reported that there are no guarantees that the

international assistance effort will result in safer reactors or expedite

the closure of the riskiest reactors.\1 In fact, in the absence of a

commitment to close down the reactors, the assistance may encourage their

continued operation. We noted that donor countries face formidable

challenges in promoting the closure of the Soviet-designed reactors

because the countries operating them depend on the nuclear power to meet

their needs for domestic energy and export income.

5. We agree that the new evaluation system is promising in that it should

provide an improved basis to evaluate USAID's programs in the NIS.

However, since the first report is not due until November 1995, it is too

early to know whether the system will fulfill its promise. The value of

the system will depend on the indicators selected, the reliability of the

data, and the subjective judgments of USAID officials preparing the

reports. For the system to have credibility, USAID will have to be able

to identify shortcomings as well as successes.

6. We have modified the report to reflect this information.

7. We were able to reconcile obligations and expenditures in the USAID

financial report with other USAID documentation. Accordingly, we have

deleted the examples from the report.

8. Our draft report included information on the work of the Consuls

General. We have modified our report to update the information on

increased site visits.

9. Although market forces played a role in the limited use of some of the

centers, the lack of local support as well as other factors also caused

the low activity levels at some centers. More importantly, it is

questionable whether USAID should spend funds on activities without a

market unless it has a strategy to create demand for the product it is

financing.

10. We visited only one site (in Siberia during February) because of the

limited amount of time we had in country. Vorkuta can be reached by plane

in the winter. USAID can visit the sites at other times during the year.

We believe that three site visits--two occurred after we began our

audit--in 31 months is inadequate for monitoring purposes. Day-to-day

contacts with PIER staff are important; however, they do not substitute

for site monitoring or provide USAID with an objective basis for

evaluating the project's success.

11. The accomplishments noted in our report are those that have had the

greatest impact. PIER did not provide us with any statistics that

indicated increased mine safety or productivity. Moveover, a September

1994 study produced by the U.S. Department of the Interior indicates that

mine safety in Russia is actually getting worse. The beneficiaries we

spoke with indicated that they were implementing new mining methods

introduced by PIER; however, they did not mention any measurable increases

in productivity. In addition, although productivity and efficiency are

important, overall production for the coal sector is still too high.

Finally, PIER's Moscow director stated that this project has had the

greatest impact in the areas of restructuring, private sector involvement,

and social safety net development.

12. Our report does not state that an interim evaluation is imminent and

may lead to activities being redirected. Our report states that "USAID

management admitted that no annual assessments or midterm evaluations were

conducted," even when required by the cooperative agreement.

13. USAID's new procedures did not affect the program during the time

frames we reviewed. Also, the work plan example should be taken in the

context that several iterations of the plan have been submitted and

revised since November 1994.

14. Our draft report did not recommend that more authority be delegated.

15. Our report was modified to show that the Ministry of Environmental

Protection and Natural Resources was involved in the initial selection of

project activities. However, the Ministry did not participate in

designing the projects as USAID suggests. USAID acknowledges the almost

immediate shift of its relationship from the central to the local

government once the projects were selected. We remain concerned over the

lack of federal involvement, especially regarding the provision of

resources and the limited potential for replicability. We believe that

without outside funding or support from the federal level, sustainability

and replication will be difficult.

16. As indicated in the report, we found that as of February 1995, the

Far East project had contributed little to systemic reform and is

unsustainable without outside funding. The report discusses the project's

attempt to address systemic reform through efforts to maintain and restock

the forestry base.

17. As indicated in the report, the deliverables identified in the

delivery orders generally cited reports and studies as the results. We are

unable to verify USAID's statements regarding the project's results.

18. Although we recognize that this project was only one of many in the

energy sector, we found that the project is unlikely to contribute to

systemic reform because of its design and the lack of monitoring and

follow-up by USAID.

19. USAID suggested that we select this project in part because USAID

represented it as a success, based on an independent evaluation. We

visited only Yekaterinburg for two primary reasons: USAID suggested that

it was a good site to visit and it was one of only two cities where

equipment was installed and extensive energy audits and training were

provided. However, as we reported, the equipment had not been installed.

USAID's assertion that our conclusion is based almost entirely on the site

visit is wrong. Our conclusion is also based on discussions with

representatives from RCG-Haggler Bailly, Joseph Technology, Honeywell, and

USAID officials responsible for the project and our review of numerous

documents on the entire project.

20. We did not make statements or draw conclusions about other projects

in the program or about the overall program. We noted that there was no

indication that the project we reviewed had contributed to systemic

reform. The energy efficiency audits and demonstration sites can only

have an impact on systemic reform if USAID ensures that (1) equipment is

installed; (2) equipment and training is used; (3) the recommendations in

the energy audits are implemented; (4) the results of the project are

monitored, recorded, and publicized; (5) appropriate personnel have access

to the demonstration sites; and (6) problems such as lack of equipment

certification are corrected. At the time we conducted our fieldwork,

USAID was not ensuring any of these elements because the project did not

include any mechanisms for long-term monitoring or replicating the

project. USAID, in its comments, acknowledged that the project alone is

unlikely to have an impact on systemic reform.

21. We agree that the dollar value of the uninstalled equipment

constitutes a relatively small percentage of all the equipment purchased.

The fact that USAID was unaware of the problems in Yekaterinburg and had

not monitored whether any cost savings had been achieved and did not know

whether any systemic improvements had resulted from the equipment, energy

audits, and training provided is the issue.

22. The consultant's evaluation indicated that all of the equipment was

installed in April 1993. The documents we reviewed indicate that the

equipment was provided in April and May 1993. If the equipment did not

arrive until June 1993 as USAID suggests, USAID should have known the

evaluation had problems when it indicated that all the equipment was

installed 1 or 2 months before the equipment ever arrived.

23. We contacted individuals who were identified as participants by

USAID-Moscow.

24. Our conclusion that the training was irrelevant was not based on our

discussions with the participants of the PIET training courses. It was

based on statements by various USAID officials, including the USAID-Moscow

Mission Director and the Chief of USAIDWashington's Europe and the Newly

Independent States- Health and Population Office. For example, USAID

officials told us that a 2-week training course without follow-on

activities could not be expected to result in any systemic reform. In

addition, as we also noted in the report, because USAID had not conducted

any long-term monitoring of the participants, it had no evidence that any

of the participants instituted systemic changes based on the training.

The opinions and views of the participants we interviewed were used to

provide insight as to why no systemic changes had occurred.

25. Contrary to USAID's comments, we referred to the course evaluations

in our draft report. We stated that ". . . most participants were

satisfied with the course and believed it was applicable to their work

conditions." However, our assessment was not concerned with whether the

participants were satisfied with the course but with whether the goals of

the PIET contract and the Freedom Support Act were fulfilled.

26. We question USAID's assertion about the actual positive impact of the

training and follow-on assistance. First, at the time of our review,

follow-on assistance was not planned to begin for another 6 months and no

assessment had been completed to confirm or deny USAID's assertion.

Second, despite repeated USAID statements that the Siberian participants

were involved in follow-on projects, USAID project officials did not know

how many were actually involved. When the contractor compiled this data

for us, the USAID project official in charge of the program was surprised

that 75 percent of the participants in Siberia were not involved with the

planned follow-on activities. Finally, USAID health officials we spoke

with were unanimous in their assessment that the follow-on project's

progress to date has been a disappointment.

27. Contrary to USAID's assertion, we met with the Russian Privatization

Center (RPC) official responsible for the project. This official

questioned the competence of some of the consultants.

We also believe that the characterization of this project as a qualified

success is an overstatement. Project task orders were never modified,

thus the focus of the project remained to increase the availability of

commercial real estate. However, after project completion, large amounts

of commercial real estate continued to be leased in the selected cities

under conditions that encouraged inefficient use, and the municipalities

failed to maximize revenues.

Furthermore, we noted that the Center, in one of the memorandums quoted by

USAID, questioned the reliability of IBTCI representations and indicated

that USAID and the Center believed that the Perm' model was being rolled

out to the other cities. The memorandum stated the following:

At our most recent meeting, on June 2, Jay Kalotra [the project director]

presented a preliminary draft of the wrap-up memo for the project. At

that time, I reminded Jay several times that deviations from the Perm'

model would have to be rigorously defended to both USAID and the senior

management of the RPC. Jay's response was that IBTCI deviated from the

Perm' model in large part because the model was ill-suited to the chosen

roll-out cities. To a considerable extent, this may be true. However,

this obviously does not exonerate IBTCI, since their task was to find

cities where a pure roll-out could be performed. [underscoring supplied]

In its most recent memos, IBTCI suggests that they told us at the outset

they would adopt a broader approach than BCG took in Perm'. While it is

true that IBTCI states some very ambitious goals, it is disingenuous to

suggest that we agreed to replace the Perm' model with something else. .

. . [underscoring supplied]

However, as noted above, even three weeks ago IBTCI was maintaining the

pretense of Perm'-style results. And it was only when we actually visited

the project sites that we could see the extent to which deviations had

occurred. [underscoring supplied]

IBTCI was clearly responsible for selecting the cities. GKI relied on the

contractor, but GKI's approval did not relieve the contractor of this

responsibility. Because the contractor did not attempt to use the Perm'

model during the roll-out phase, it is impossible to determine if the

Perm' model could be applicable to the other cities.

28. Our report draft specifically stated that the IBTCI team spoke

Russian and had meaningful business experience. The issue was IBTCI's

awareness of local conditions in order to replicate the Perm' model.

Although the project manager on the roll-out was also the comanager for

the pilot, none of the city team leaders had worked on the Perm' pilot.

29. Our analysis casts doubt on whether the entire project can have a

systemic impact if the individual partnerships are not having an impact.

30. We did not assess the activities of CNFA because the USAID Inspector

General was evaluating CNFA's work. Discussions with the USAID Inspector

General's office indicate that some of CNFA partnerships are experiencing

problems and consequently are not contributing to systemic reform. In

addition, CNFA's August 1994 evaluation of the agribusiness partnerships

project indicates that the overall project had not achieved the desired

results. Also, USAID's February 1995 review of the agribusiness

partnerships states the following:

It is not realistic to expect the agribusiness partnerships program to

have a significant, measurable impact on overall food systems in the NIS.

The limited number of partnerships being supported suggests such national

level impacts are unlikely during the life of the activity, if ever.

USAID-Moscow staff stated that the agribusiness partnerships project could

not by itself influence systemic reform.

31. Although TVG has established three partnerships in Russia, only one

(Petoseed) is functioning. According to TVG staff, CTC Foods has run into

financial problems; consequently, its potato processing facility may never

be constructed. Finally, the third partnership (Big Sky Foods Trading,

Inc.) has only recently been approved, and it is too early to determine

whether this project will be successful.

32. USAID staff in Moscow and Washington characterized the project as

discontinued because no more partnerships can be introduced and no more

funds will be obligated.

33. USAID-Moscow staff said TVG had not performed adequately and had not

identified appropriate partnerships. The documents we reviewed also

indicated that TVG was not performing well.

34. Our report includes examples of the causes for delays in the approval

process, including the need to deal with legal issues.

35. We modified the report to reflect this foreign policy goal. However,

the primary objective for the pilot project announced in April 1993 did

not focus on relocating officers from the Baltics. The announcement made

in July 1993 focused the program on the removal of officers from the

Baltics.

36. USAID is incorrect in stating that the oblast' was involved in

signing the memorandum for Novosibirsk. It was only signed by USAID and

the municipality of Novosibirsk.

Nuclear Safety: International Assistance Efforts to Make Soviet-Designed

Reactors Safer (GAO-RCED-94-234, Sept. 29, 1994).

MAJOR CONTRIBUTORS TO THIS REPORT

NATIONAL SECURITY AND

INTERNATIONAL AFFAIRS DIVISION,

WASHINGTON, D.C.

Louis H. Zanardi

Eugene D. Beye

Edward J. George, Jr.

EUROPEAN OFFICE

Peter J. Bylsma

David M. Bruno

Jodi McDade Prosser

Go to TOP of this page


RETURN to Palms' Lobby RETURN TO HOME PAGE




Palms & Company, Inc.: Palms Bayshore Building, 6421 Lake Washington Boulevard Northeast South, Kirkland, WA 98033-6876;
http://www.peterpalms.com
Phone: 1-425-828-6774 & 1-425-827-5528
Copyright 1995, Palms and Company, Inc.; all rights reserved; email: palms@PeterPalms.com